29/01/2025
QHOME 2 - Stage of construction (January)
The zero cycle of the building has been completed - basement with underground garages, parking spaces, transformer station, technical and storage rooms. This includes poured concrete, waterproofing, foundation slab, basement walls and columns, including a reinforced concrete slab at -0.25 m. /the slab that represents the floor of the ground level and is located at ground level/. Vertical elements are currently being implemented - columns, vertical belts and earthquake washers, up to +2.85 m. These are the vertical elements up to the first slab above the ground.“ Do not miss the opportunity to choose a property in the **QHome 2 building with energy class A**. Your new home is designed with underfloor heating and a connection for installing a heat pump in each apartment. We offer flexible payment plans, with the possibility of financing ACT 14. **Comfort of living is guaranteed with the highest class materials that we use:** **Functional design and layouts of the apartments.** **Project by I/O Architects** Between the apartment walls are implemented with the special **WIENERBERGER** system for sound insulation type 12+5+8cm (**Wienerberger POROTHERM 12 N+F**; Stone wool - 5cm) Aluminum joinery **Reynaers Masterline 8** with triple glazing: external: 8mm 70S HT tempered PVC spacer, medium: 5mm clear PVC spacer, internal: 5.5.2 Low-E Elevators **Thyssenkrupp** A heat and sound insulation pad made of XPS is laid under the screed in the rooms of the apartments. In this way, the screed and subsequent flooring on it is separated from the slab and the walls and rooms are protected from impact noise that is transmitted through hard surfaces (the reinforced concrete structure of the building). ------------------------------------ Deadlines: ACT 14 April 2025, ACT 15 April 2026, ACT 16 July 2026.
20/12/2024
Residential building "QHome" was awarded a prize in the "Green Buildings" category at the National Competition for "Building of the Year 2024"
14/10/2024
QHome 2 - Stage of construction
**08.2024** - Fortification and mass excavation completed. According to the agreed technical project, the reinforcement is planned to be of the "Berlin Wall" type with 2T metal profiles laid in drilling trenches, as well as wooden planks between the profiles. Excavation is carried out vertically, along the regulatory line of the property. Underlay concrete is executed with foundation slab preparation. According to the linear schedule, the zero cycle should be completed by the middle of November. Do not miss the opportunity to choose a property in the Qhome 2 building with energy class A. Your new home is designed with underfloor heating and an outlet for installing a heat pump in each apartment. We offer flexible payment schemes, with the possibility of ACT 14 financing. **Living comfort is guaranteed with the highest-class materials we use:** - Functional design and distribution of the apartments. - Project by I/O Architects - Between the apartment walls are made with the special WIENERBERGER system for sound insulation - type 12+5+8cm (Wienerberger POROTHERM 12 N+F; Stone wool - 5cm) - Reynaers Masterline 8 triple glazed aluminum windows: external: 8mm 70S HT toughened PVC spacer, middle: 5mm clear PVC spacer, internal: 5.5.2 Low-E - Thyssenkrupp elevators - Under the screed, a warm and sound-insulating XPS pad is laid in the rooms of the apartments. In this way, the screed and its subsequent flooring on it is separated from the slab and the walls and rooms are protected from the impact noise that is transmitted through the hard surfaces (the reinforced concrete structure of the building). - **Deadlines: ACT 14 - April 2025; ACT 15 - April 2026; ACT 16 - July 2026**